In the coming weeks, much ink will be spilled on the permitting reform bill: The Bipartisan American Affordability and Jobs Act of 2026 (BAAJA). BAAJA—negotiated by Senators Lee, Heinrich, Capito, and Whitehouse—contains 417 pages of dense material. It covers two broad topics: procedure and energy.
My expertise is on the procedural side of the bill. Accordingly, my goal in this piece is to provide a short, albeit somewhat technical, explanation of what the procedural aspects of BAAJA would do if enacted.
In short, my view is that the bill would do an extraordinary amount of good if enacted. And it does so in a way that has broad, bipartisan appeal. Which makes sense, given the four senators who negotiated it.
The Problem
The term “permitting” is unclear; it refers to a range of different issues generally clustered around building things in the physical world. One set of issues regards the substantive law of what private actors are allowed to do at all. (Think: limits on emissions, or how costs are allocated among those who benefit from what is built.) Another set of issues regards the predicate steps that the government must take before doing something, or allowing something to be done, in the physical world. That latter set of issues are what I mean by permitting procedure.
One big motivation behind the push for permitting reform is the widespread sense that procedural issues in permitting are broken. That is, getting approval to act—both in the private sector and in the government itself (say, forest management)—takes too long, is too costly, and is too uncertain. These delays and costs are largely driven by anticipatory efforts to comply with, and reduce litigation risks under, certain procedural statutes.
This general view is correct: there is strong evidence that a set of procedures that began to be enacted in the late 1960s have caused enormous yet little-understood harm. In past work, I have referred to these procedures as “hostile turn” procedures because they were born of widespread distrust of government—inflamed by its failures in that era—and a faith that more stringent procedures would always improve outcomes. Hostile turn procedures are distinctive because they require agencies to do additional analysis or public engagement before acting, enforceable via judicial review, beyond what was already required in the Administrative Procedure Act (APA). The harms of the hostile turn have come into increasing focus over time. For example, these procedures led the cost of interstate highway construction to spike. Indeed, hostile turn procedures are why building new highway lanes (which trigger hostile turn procedures) has gotten much more expensive than input costs, whereas repaving highway lanes (exempt from them) has not. More generally, evidence indicates that these procedures led construction productivity to not only stop improving around 1970, but to start going backwards. Construction is a large enough share of economic output that had construction productivity gone from falling 1% per year to instead growing by 1% per year—not a dramatic hypothetical—average income per person in the United States would be about 10% higher today as a result. The additional opportunity costs stemming from government effort spent on complying with these procedures rather than doing more valuable work are likely massive, but are far more difficult to quantify. Damningly, there is no reason to believe that these hostile turn procedures have any substantial benefits over those already provided by the APA.
The most important hostile turn procedures that stymie projects in the physical world are the National Environmental Policy Act (NEPA),1 the National Historic Preservation Act (NHPA),2 and the little-known procedural consultation requirements of the Endangered Species Act (ESA). BAAJA’s procedural provisions are primarily about amending these statutes, as well as a smaller portion amending the Clean Water Act.
But the APA is important to understand before turning to BAAJA, even though it is only glancingly referenced in the text of BAAJA. After all, prior to the enactment of NHPA in 1966, NEPA in 1970, and ESA in 1973, the United States federal government did not rule by unconstrained fiat. The APA settled and generalized the basic system of administrative procedure that had developed as the first era of administrative procedure broke down at the end of the 19th century. Relevant to BAAJA, the APA allowed for anyone wronged by agency inaction or action to compel agency action unlawfully withheld or unreasonably delayed, or to block unlawful agency action. The APA empowers courts to stop agencies from acting in a manner that is arbitrary or capricious, violates a regulation, violates a statute, or violates the Constitution. The APA was broadly successful at creating a capable and constrained government, including in the two decades from its enactment to the start of the hostile turn. The reformers who developed the hostile turn procedures were reacting to real failures, but they were not failures of the APA.
The Solution
Procedures that force agencies to act reasonably, supported by high-quality evidence and without improper motive, are incredibly valuable. Indeed, without them, government abuse often follows quickly. But procedures that have at best a very distant relationship to the reasonableness of government action tend to have enormous costs and very few benefits. Accordingly, by retaining or strengthening procedures focused on reasonableness and related concerns while weakening or eliminating other procedures, we can have a government that is massively more effective—burdening both the private sector and civil servants far less—while also reducing abuses of power.
Judicial review is the dominant means by which procedural constraints are enforced.3 Accordingly, it is important to tailor judicial review to ensure that agencies follow the law without risking a juristocracy. Moving more judicial review of agency actions upstream (so-called “pre-enforcement review”) as well as having challenges heard in circuit courts (bypassing district courts) speeds consideration of legal issues. Moving cases to circuit courts (or ideally, the expert D.C. Circuit) has another benefit: it reduces judge and forum shopping that empowers the most extreme judges in the country.
Finally, state and local laws can be important impediments to realizing national priorities. Renewable energy developers, for example, generally rank state and local impediments to building as more important than federal ones. By limiting state and local governments’ ability to block projects for arbitrary or capricious reasons—porting over that part of the APA, in essence—we could do a great deal to stop unreasonable efforts to thwart national priorities without infringing on the proper role of state and local government.
How BAAJA Fixes Much of the Problem
Focusing Procedures on Reasonableness
Remedies
The most important reform in BAAJA is that violations of NEPA and NHPA can no longer be the basis for stopping a project. Instead, if a court finds a violation, it remands to the agency to correct the error (e.g., provide a more complete analysis of the action’s effects on the environment or historic places). The project continues as the agency corrects the error.4
This might sound scary and unwise. But remember: the APA still allows anyone wronged by an unreasonable (arbitrary or capricious) action to stop that action, or to force the agency to act if the problem is a delay in agency action.5 So if an action harms the environment for little benefit, or for easily avoidable benefit, an APA suit would stop it regardless of NEPA.6 The bizarre aspect of the hostile turn procedures is that even when there is little to indicate that the agency’s action was wrong on the merits, litigants can generally block actions anyway. BAAJA ends that. It should be roundly cheered for doing so.
Scope and Who Can Sue
BAAJA also makes some tweaks to the scope of what NEPA and NHPA apply to.7 But in truth, these changes are unlikely to matter much. There is a long history of making such tweaks; analogous efforts go all the way back to the Carter administration. The Fiscal Responsibility Act of 2023 made very similar amendments to NEPA (e.g., limiting NEPA to actions “subject to substantial Federal control and responsibility” and excluding cases of minimal federal funding or mere provision of loans). But the Fiscal Responsibility Act did not fix NEPA.
Some of BAAJA’s tweaks may help at the margin. It reduces duplicative NEPA work across agencies, and it codes in some formal size triggers for whether or not NEPA applies (e.g., where the federal financial contribution is under $50 million). Other of BAAJA’s tweaks may be a mixed bag. For example, when there is a public comment period, only those who submitted a public comment that is sufficiently detailed can bring a NEPA, NHPA, or CWA suit on the topic of the detailed matter. This could help reduce low-value litigation, or it could lead agencies to get snowed under many duplicative and highly detailed comments. The most likely outcome is that neither happens, and these tweaks all have little effect, because few would bother to sue under NEPA and NHPA once they can no longer be used to block a project or action.
The Clean Water Act
As noted above, BAAJA amends the Clean Water Act (CWA) as well as NEPA and NHPA. While the CWA is not a “hostile turn” procedural statute, it grants states a role in approving certain projects with few guardrails, making those powers prone to abuse. It may be a surprise after a long discussion of the role that bad procedure played in the hostile turn, but BAAJA solves this by tailoring the authority of states and imposing new procedural constraints. States—which currently are not effectively constrained under the CWA—are restricted under BAAJA to make certification decisions only on the basis of whether a project complies with water quality requirements.8 Under BAAJA, a state can only justify a certification denial if it is not possible for conditions to satisfy water quality standards, and can only condition approval if the conditions are necessary to ensure water quality compliance and there are no less burdensome conditions that could do the same. BAAJA also imposes deadlines on states in making these decisions.
Public Engagement
BAAJA is not reflexively anti-process or anti-public input: for example, it requires EPA to set water quality standards via notice and comment rulemaking. Notice and comment rulemaking is appropriate for this kind of binding broad-spectrum standard setting: its costs are justified by its benefits, namely that civil society experts can force agencies to explain their decision in light of the high-quality submitted evidence. In that way, notice and comment rulemaking supports the APA’s requirement that agencies not act arbitrarily or capriciously.
Conversely, BAAJA trims the 90-day ESA consultation period down to 60 days. This is an improvement; in fact, there is very little reason to believe that this type of consultation (unlike public comment on substantive rules) has much value. Consider that from January 2008 to April 2015, of the 88,290 actions subject to ESA consultations with the Fish and Wildlife Service, only one consultation required a modification of the project (which then went forward, in slightly modified form). Similarly, BAAJA cabins both ESA and NHPA consultations by requiring that they conclude within 145 days or by the end of the NEPA process (when applicable), which limits the upper tail of potential delays.
Regrettably, BAAJA makes public input in NEPA incrementally worse, preserving low-value project-by-project public comment requirements on each notice of intent to prepare an environmental impact statement (EIS) and imposing a new minimum 45-day comment period on them.9 Public comment has far fewer benefits when focused on a specific project in a limited geographic area, but similar costs. Regardless, there is no reason to impose a 45-day comment period for intent to prepare EIS when the most important rulemakings only require a 30-day comment period.
FERC and Benefit-Cost Analysis
One promising, albeit isolated reform is the direction that FERC conduct a rulemaking that requires utilities to conduct a benefit-cost analysis of deploying advanced transmission technologies on a recurring basis. If the benefits exceed the costs, utilities are required to deploy those technologies, on a timeline set by FERC. Benefit-cost analysis of this kind is a powerful tool for constraining abuses of power, incentivizing civil society to generate better evidence on the question, and directing federal agencies to adopt the most socially beneficial policies.
Standard for Review
One place where BAAJA differs from my preferred approach is in several contexts requiring that an agency (or state) show by “clear and convincing evidence” that something is the case, rather than allowing the action to stand unless it is arbitrary or capricious (a less demanding standard).10 The optimal place to set the bar on reasonableness certainly varies with the circumstance; perhaps these contexts will benefit from making it easier for litigants to succeed in challenging agency action. But whether or not “clear and convincing evidence” turns out to be a bit too strong, BAAJA is focusing on the right question: how stringently should courts review the reasonableness of agency action? (Rational basis? Arbitrary or capricious? Clear and convincing evidence?) It is a marked change from the mistaken approach of the hostile turn.
Ensuring Legality While Avoiding Juristocracy
How Courts Hear Cases
The second most important change in BAAJA, after the remedial change to NEPA and NHPA, is moving NEPA and NHPA suits (and CWA suits regarding the scope of the much-litigated term “waters of the United States”) to circuit courts.11 Ensuring that circuit courts can quickly hear cases (where district courts are not needed to develop the record) reduces delay with no meaningful downside. More importantly, it reduces the forum and judge shopping that allows the most extreme judges on either side to exercise inappropriate influence on governance. Even better, ESA cases regarding biological opinions are channeled to the D.C. Circuit, which tends to produce a consistent and high-quality body of administrative law.
Another positive shift in the bill directs courts to expedite their consideration of cases brought under NEPA and NHPA. Because the cases that will be brought following BAAJA’s amendments will (almost exclusively) be seeking preliminary injunctions due to imminent harm or addressing unreasonable delays or denials, it is reasonable to pick these cases out as priorities. Often, courts do move quickly to address such cases without being required by statute to do so. But mandating expedited consideration of cases helped ensure that the Telecommunications Act of 1996’s provisions barring unreasonable denials of cell phone towers succeeded.
Permit Certainty
There is an elaborate set of efforts in BAAJA around what has been nicknamed “permit certainty,” which broadly refers to efforts to avoid bad faith delays or denials of disfavored projects.
First, on NEPA delays, the Act requires agencies to notify project sponsors within 60 days of submission if their applications were complete, or if incomplete, request in writing the additional information that the agency needs to determine that the application is complete. Requiring the reasoning to be in writing provides a useful focus for an APA suit alleging that the requirement to submit additional information was arbitrary or capricious. Indeed, requiring a written reason that can be reviewable was one of the key innovations of pre-APA federal administrative law and the Telecommunications Act of 1996’s state and local cell phone tower provisions. Under various BAAJA provisions, if an agency blows past NEPA, CWA, or ESA deadlines, a project sponsor can more easily bring a suit over the delay. BAAJA also has a fun provision requiring that the head of any agency that has a delay that has lasted for more than 60 days in excess of some of the deadlines may not travel more than 25 miles away from their “duty station”; this is the kind of aggressive remedy that gets a cabinet secretary’s attention quickly and may well push them to avoid bad faith delays.12
Second, on revocations, terminations, and alterations (and the like) of authorizations or permits, BAAJA requires that the government justify the action on narrow grounds. Only a court order, material breach of the terms of the authorization/permit or violation of applicable law, obtaining the authorization or permit fraudulently, or a need to “prevent specific, urgent, substantial, and proximate harm or damage to life, property, national security, or defense that is based on new information” can justify the action (absent consent of the project sponsor). It is unclear how effective these provisions will be, given that allegations of violations of applicable law or national security concerns have recently been the basis for unjustifiable terminations of authorizations. But if a project sponsor shows that the agency action does not fall into one of these categories, they are entitled to not only an injunction but also a requirement that any further agency action of the type be pre-approved by the same judge along with reimbursement of attorneys fees and costs, any costs that arose from the delay, and 25-50% of the remaining (otherwise uncompensated) project costs incurred to date.13 If there is a pattern of disparate treatment of a particular type of energy related project (assessed relative to the treatment of such projects over the previous five years)—unreasonable delays or improper denials—that persists long enough, project sponsors can get larger payments, including 50-100% of all of the remaining (otherwise uncompensated) project costs (i.e., including those that are expected, but not yet incurred).
These efforts may be limited in their efficacy. But to the extent that they are effective, they will help reduce the scope of, and temptation to engage in, abuses of power. In that way, they illustrate how more constraints on government (here: special procedural constraints on certain types of agency action) can speed up government, improve the quality of its actions, and reduce abuses of power. These outcomes are not always in tension with one another.
Ensuring that State and Local Governments Do Not Thwart National Priorities
BAAJA takes some important steps forward in addressing state and local “NIMBY” problems. Much of this occurs at the intersection of transmission and procedure. One major change is that long-distance power lines outside of DOE-designated corridors no longer require the approval of every state (including localities, where devolved power by the state) that the project transits. BAAJA instead allows developers of a transmission project to go to FERC simultaneously with their application to state governments, and if the states do not approve the project within a year, FERC is required to approve the project if FERC determines it to be in the national interest. Another change ensures that when states are making federal law determinations on transmission, their actions can be challenged in the same manner as action by a federal agency.14 That allows ordinary APA cases to be brought against states in the same courts that they would be brought against agencies. This echoes the successful approach of the Telecommunications Act of 1996.
An even lighter touch is taken on state and local approvals of installing “behind-the-meter” technologies like rooftop solar and batteries. BAAJA sets up a program whereby DOE will provide technical assistance, financial assistance, and financial prizes to encourage state and local governments to adopt exemplary streamlined permitting or voluntary inspection approaches, funded by $20 million a year from fiscal year 2026 to 2031. Such voluntary inducements may have limited success in shifting behavior, but to the extent they succeed, they will do great good. A different approach is taken with utilities: they are required to interconnect these types of “behind-the-meter” resources, but states are left free to create generally binding exceptions.
What BAAJA Will Not Fix
BAAJA would be by far the largest and most positive reform to hostile turn procedures since they were first enacted. Its reforms can be built upon in future legislation to make similar, broader administrative procedure reforms down the line.
But even after BAAJA, state and local governments will play a large role in stopping important energy and other infrastructure from getting built. This is no small matter. As of the summer of 2025, at least 20% of counties have “heavily restricted or outright banned” the “development of new wind and solar power plants”—“roughly 17% of the total land mass of the continental United States.” More work remains to be done on leaving appropriate state and local authority in place while prohibiting unreasonable restrictions on national priorities (like safe and affordable energy generation).
Because BAAJA is a “permitting” bill, which addresses what the APA defines as “adjudications”—authorizing a particular solar farm to begin construction, completing an environmental analysis in advance of a particular prescribed burn, determining if a particular natural gas pipeline threatens water quality, etc.—the broken aspects of the other APA category, rulemakings, goes unaddressed by the bill. For example, hybrid and formal rulemaking requirements make rules take substantially longer to complete for no appreciable improvement in rule quality. Statutes like the Regulatory Flexibility Act and the Small Business Regulatory Enforcement Fairness Act will continue to burden many agency rulemakings, with no evidence that they provide benefits relative to the APA baseline.
Another category of work that remains concerns reforms to the APA itself. For example, the APA directs courts to forgive harmless errors, but that provision has long been gutted by judicial interpretation; it can and should be given its original heft. Similarly, while BAAJA makes important strides towards reducing judge and forum shopping, far more could be done to ensure that suits seeking to block federal actions are not brought before the most extreme judges in the country. And while BAAJA directs more cases to circuit courts, a more general fix of that kind is needed. Finally, holes in the APA itself—in particular, the fact that the APA does not fully apply to statutory authorities directly vested in the President and discretionary spending actions that fall within the rule of Lincoln v. Vigil15—can be exploited to shield abuses of power from judicial checks.
Conclusion
Enacting BAAJA would be a triumph. Often, people are suspicious of claims that a reform can be good for liberals and conservatives alike. But our current system of procedure is so broken, and so flawed, that there ought to be no dispute here. There is much work to do peeling back useless procedures that impose delays and costs across the private sector and government agencies, while strengthening the high-value and essential procedures that protect against abuses of power and incentivize high-quality policymaking. BAAJA is a great start.
More specifically, section 102(2)(C) of NEPA and related provisions.
More specifically, section 106 of NHPA and related provisions.
In a small set of cases, congressional or popular pressure may be brought to bear to force compliance with procedural requirements. But that is vanishingly rare; such pressure generally focuses on outcomes, not process. And even then, very few actions are salient enough to spur substantial legislative or public engagement.
For those cursed with the knowledge of niche administrative procedures, it may be helpful to put it this way: BAAJA “UMRA-izes” NEPA and NHPA. That is, the Unfunded Mandates Reform Act (UMRA) requires agencies to produce a “qualitative and quantitative assessment of the anticipated costs and benefits of the Federal mandate, including the costs and benefits to State, local, and tribal governments or the private sector, as well as the effect of the Federal mandate on health, safety, and the natural environment” for certain rules that they issue. 2 U.S.C. § 1532(a). But—like BAAJA, and unlike most hostile turn procedures—“the inadequacy or failure to” do so “shall not be used as a basis for staying, enjoining, invalidating or otherwise affecting such agency rule.” The remedy is instead having the agency produce an adequate assessment. 2 U.S.C. § 1571(a).
BAAJA actually has a belt-and-suspenders approach here: it allows issuance of a preliminary injunction if an agency violated a federal law (other than NEPA and NHPA) or doing so is necessary to prevent irreparable harm as well as consistent with the public interest and balance of equities (the Winter factors, 555 U.S. 7 (2008)). But at least at first blush, I do not think that these provisions actually matter: to get a preliminary injunction in an APA case alleging that an action is arbitrary or capricious, one has to satisfy the Winter factors as well, prior to final disposition on the merits. There should not be a case where the public interest and balance of equities exist in one case but not the other. Of course, in APA cases, courts often move directly (and expeditiously) to summary judgment and a remedy of vacatur rather than an injunction, but that is just another reason why these BAAJA provisions will not matter much.
That is why of all of the alleged abuses of power during the second Trump administration, it seems that almost none were stopped by NEPA, while many have been stopped by the APA.
Another tweak is that NEPA, NHPA, and CWA litigation must be brought within 150 days, but this likely is an unimportant tweak given litigants’ usual desire to bring suit before any work on a project begins. Courts are also directed to “afford substantial deference to the agency” in NEPA cases, but it is not clear if that adds much to the decision in Seven County. 605 U.S. 168 (2025).
In my view, this is not first-best. As I discuss below regarding the advanced transmission technologies provision, it would be better to direct that the decision be based on a determination that the project’s benefits exceed its costs. If some of the important costs occur because of air quality effects rather than water quality effects, they should not be ignored. The provision nevertheless has virtues that a total lack of constraint lacks. For the same reason, BAAJA’s provisions limiting states’ review of interstate transmission lines and pipelines to their direct discharges is likewise not ideal. Indirect water quality impacts—whether benefits or costs—may be important to consider. Yet another CWA amendment has a similar structure, limiting the Army Corps of Engineers to analyze the discharge of dredged material into U.S. waters only with reference to water quality impacts. In my view, it would be best to consider all material benefits and costs of dredged material discharges. Nevertheless, in evaluating BAAJA, it is important to recall that it represents a bipartisan compromise and to consider the limits of what is politically feasible.
It also imposes a maximum comment period of 60 days, or 75 with sponsor agreement. A similar 45-day public comment period is required for FERC transmission permits actions.
Another place where BAAJA differs from my preferred approach is in limiting suits challenging a permit issued under the CWA unless the activities authorized by the permit would present an imminent and substantial danger to human health or the environment for which there is no other equitable remedy available under law. This seems unwise; if the permit was unlawful because it is inconsistent with water quality requirements, it is not obvious why legal remedies should wait until harm is imminent.
Circuit courts are granted original and exclusive jurisdiction over such claims, and supplemental jurisdiction over any related claims.
Likely sensibly, the Secretary of Defense is exempted from this provision. But conversely, it allows an administration that desires to overcome these “permit certainty” efforts to more effectively do so via the Department of Defense, an approach that the second Trump administration has already taken, with mixed success. Below, note that national security and defense concerns are explicitly blessed as potential grounds for revocation, termination, or alternation of an authorization or permit; accordingly, BAAJA may funnel more such efforts through the Department of Defense.
I.e., in the circuit courts. More on why that is good above.
508 U.S. 182 (1993).